04.02.2013
In total, Pskovenergo commissioned approximately 50 MVA of capacities and over 416 km of grids In 2012, CAPEX of Pskovenergo branch of IDGC of the North-West, JSC of capital construction, Technical re-equipment and reconstruction of the region electric power grid network facilities made 950.2 mln RUR. This exceeds the amount of corresponding expenditures incurred in 2011 by 70 mln RUR.
In total, Pskovenergo commissioned approximately 50 MVA of capacities and over 416 km of grids which is equal to 147% of the enterprise plan. The investment projects implemented were predominantly aimed at technical connection of privileged category applicants (up to 15 kW) and technical re-equipment of the grids with account for the growing needs of the region.
Among the largest facilities are construction of grid infrastructure for power supply of “Yunost” sport camp in the Ostrovsky District, pig-breeding sites in the Nevelsky District, the regional oncologic hospital in Pskov, the museum-reserve “Izborsk”, the Pskov Academic Drama Theatre named after A.S. Pushkin, new Residential Neighborhood No. 12 in Pskov and a number of others.