Until the end of the current week, Vologdaenergo branch of IDGC of North-West plans to complete construction of Airport Neighborhood 10/0.4 kV overhead line (Vologda Region) amounting to 5.5 mln rubles.

17.07.2012

Until the end of the current week, Vologdaenergo branch of IDGC of North-West plans to complete construction of Airport Neighborhood 10/0.4 kV overhead line (Vologda Region) amounting to 5.5 mln rubles. The works to install five 10/0.4 kV package transformer substations (PTS) are also proceeding to completion.Until the end of this week, Vologdaenergo branch of JSC “IDGC of North-West” plans to complete implementation of investment project for construction of Airport Neighborhood 10/0.4 kV overhead line in Vologda Region amounting to 5.5 mln rubles. Working commission for acceptance of the energy facility has been appointed for July 20, 2012.
As of current date, the 0.4 kV overhead line installation is 100% completed, and the 10 kV overhead line installation is 95% completed at the energy facility. In accordance with the project documentation, self-supporting insulated wire has been used for construction of the overhead lines. The works to install five 10/0.4 kV package transformer substations (PTS) are also proceeding to completion.