21.05.2012
The power industry specialists intend to complete reconstruction by the end of 2012.Vologdaenergo branch of IDGC of the North-West, JSC has commenced implementation of an investment project for reconstruction of “Roslyatino” 110/10 kV substation in the Babushkinsky District, Vologda Region. The project CAPEX will make 169.4 mln RUR.
In the course of reconstruction of “Roslyatino” 110/10 kV substation by efforts of a contracting organization works will be performed for replacement of the equipment of the 110 kV outdoor switchgear (OSG), 110/10 kV power transformers with two 2.5 MVA transformers. Additionally, the facility will undergo replacement of 110 kV voltage and current transformers with gas-insulated ones and modernization of the relay protection equipment and telemechanics systems.
Currently, construction and installation works are in progress within the substation territory. The power industry specialists intend to complete reconstruction by the end of 2012.