16.04.2012
In 2012 one plans to spend 4.4 mln RUR on the works performance. Five substations of Karelenergo branch of IDGC of the North-West, JSC will be equipped with arching fault protections in 2012. One has planned implementation of investment project “Having Substation 6–10 kV Outdoor Mounted Factory-Assembled Switch-Gears Equipped with Arching Fault Protections”. Subject to modernization will be substations located in different districts of the republic. In 2012 one plans to spend 4.4 mln RUR on the works performance. In 2013 activities in this direction will continue. At four more substations of Karelenergo 6–10 kV outdoor mounted factory-assembled switch-gears are planned to become equipped with arching fault protections.